can someone explain the use of NOP that is into control menu? Since i have NOP on the start of the job why could someone add this Line?
NOP command
-
potis -
May 23, 2014 at 1:54 PM -
Thread is marked as Resolved.
-
-
Hi Potis , it's a clearly defined line between "Doing something" & "Not doing something " ,
"Gyro Gearloose" would be proud
Hi Potis,
Here is a reasonable answer to your question, "Instruction had to be listed somewhere". -
i think its NO OPERATION.
-
The NOP instruction is No Operation. It can be used with the PAM utility. PAM allows positions, speeds, and PL tags to be adjusted in Play as the system is running. PAM does not make the permanent rewrite until the controller executes the NOP in the job. It may take a while before the NOP at the top of the job is executed. Something could stop the job execution before the NOP is executed. Placing a NOP below a position that is commonly adjusted makes the rewrite permanent very quickly.