so i was taught to build programs under parallel starts so i can do r1-s1 and have r2 as well, so i can turn the table while in program without having to build 8 programs for a job plus table turns. but i had a contractor here my company used before me who told me that its wrong that i should use r1-r2 and then call up table turns separately. but i feel that puts to many programs in for people to screw up things. any opinions?
opinions
-
cameronsjunk15 -
April 23, 2018 at 7:07 PM -
Thread is marked as Resolved.
-
-
Hi , the bottom line is what ever works for you , just need to remember one thing , don’t make it so complex that others cannot quickly understand the methodology otherwise your making a “Rod for your own back” , ie. don’t make your self indispensable , you cannot take a holiday .
-
I think its fairly easy but no one here knows anything.The one day i was gone and they just reworked the bad weld even though i left the worlds simplest( with pictures for every step) instruction guide and they did not want to do it.