When testing a job with a DX100 controller, will Test+Interlock initiate a PStart command while testing the primary job or must the Pstart job be tested separately as a stand alone? Any info is appreciated!
Interlock + Test Start With Parallel Start Jobs
-
raccjim -
March 28, 2017 at 9:34 PM -
Thread is marked as Resolved.
-
-
Depends on a setting. Single setting will run the master task and any call jobs. Multi will run the master task, call jobs, and pstart jobs. You can change by pressing SHIFT+4, assuming since I don't see the controller generation mentioned. This can also be changed under SETUP, TEACHING COND. The wording changes between generations. Independent Next/Test or Step/Next Operation Mode.
-
Thanks for the info, I'm off-site right now and I was hoping to have something to try for next week. I was scanning some of my documentation but hadn't run across that scenario yet...