Hello,
I have a visual tracking project and i use the option "start/stop conveyor".
When i cant prevent to fill the entire line i use a DO and i stop the conveyor.
But after this i want to put one more object and restart the conveyor and not to fill the entire conveyor.
For example if i have to fill a line with 7 objects and i have filled 3 of them and i cant prevent the other 4 of them, i want to stop the conveyor.
After that i want to fill the 4th and after that i need to restart the conveyor.
The irpicktool sends me the DO until i fill all of the 7 cells.
Is any way to acknowledge the DO and restart my conveyor whenever i want?
Thanks