Configuring Digital I/O LR MATE RJ2 Controller cannot assign RACK SLOT START POINT

  • So we are trying to use the CRM5 via Honda connection to fire a solenoid with SDO 101 Connector Pin #33 on the RJ-2 MATE. When I try and configure the digital I/O per Procedure 3-1 it will change it but when I power off an on it won't take. So the configuration that I need for D0 #1 should be RACK 48(CMR5) SLOT 1 and STARTING POINT 33(SDO101) when I configure I then use the power switch on controller to cycle power.

    After power up I go look at DO #1 its is set at RACK 32 SLOT 1 STARTING POINT 5 , not where I want it. Then I cleared all I/O assignments and tried again with no luck so I checked what RACK 32 was and its the JD1A plug so I made sure no plugs were in JD1A or JD1B. I also checked system variable $RMT_MASTER was set to 0.



    HELP, anyone have any other ideas?