Hey guys,
Needing help Calibrating a new power source to my IRB 2400. I am new to ABB, efficient in Fanuc. I changed out the power source from an old one and the welds were of course not in spec. I powered down the power supply and restarted with the ROBT CAL screen ready for the Robot to run the program. I wrote the program just like the miller book shows, had some issues with the weld schedules not showing up in the screen viewer page after setting those up in the weld data screen. Anyways, even though, I ran the program and the ABB gave me an arc start failure. I was under the assumption that the Miller would take over and the ABB would not be giving these alarms under this ROBT CAL function. Is there something i missed?